Solar EPC Billing Software: Milestone Billing That Gets You Paid on Time

Teja •

The structure went up on Tuesday. The panels were mounted by Friday. Accounts found out the following Wednesday, when the client’s purchase head asked why he hadn’t received the installation invoice yet.

That gap is where most C&I and rooftop EPCs in India lose working capital. The work is done and the payment terms are sitting in the PO, but the invoice goes out late because nobody on site told the office the milestone was reached. Solar EPC billing software can close that gap, as long as each milestone is tied to the project stage that triggers it.

This post is for owners and accounts heads. It covers how solar project payment milestones are usually set up, where the cash gets stuck, and how to run milestone billing so the invoice goes out the day the work is done. If you’d rather see a working setup first, our solar EPC software page walks through one.

How solar project payment milestones are usually structured

Most C&I contracts split the payment across the life of the project. A common example:

Contracts vary a lot. Some clients push for a smaller advance. Others hold back retention money for a defect liability period, or tie the last payment to net metering approval from the DISCOM, and large clients sometimes want an advance bank guarantee before they release the first payment. Whatever solar EPC payment terms you negotiated, write them down as a schedule with one person responsible for it.

Sample milestone schedule for a 250 kWp C&I project (illustrative)

Here is the 20/50/20/10 split on a 250 kWp rooftop project, assuming a contract value of ₹95,00,000 before GST. The numbers are illustrative. Your pricing, split and tax treatment will be different.

#Milestone%Amount (₹, before GST)Triggered byProof accounts needs
1Advance on order confirmation20%19,00,000Signed PO from clientPO copy, advance BG if the contract asks for one
2Material dispatch to site50%47,50,000Panels, inverters and structure leave your warehouseDelivery challan, e-way bill, site receipt
3Mechanical & electrical completion20%19,00,000Installation checklist closed on siteSite photos, completion sign-off
4Commissioning & handover10%9,50,000System commissioned and handed overCommissioning report, handover note
Total100%95,00,000

If the contract keeps retention money, give it a fifth row with its own release date. Folded into the handover milestone, it tends to get forgotten.

Where solar EPC cash actually gets stuck

Ask the accounts head at a mid-size EPC where the money is and you’ll get a long pause, then an Excel file. When a payment is late, it’s usually for one of four reasons.

1. The milestone is reached and nobody tells accounts

The site engineer finishes installation and moves to the next site. The project manager knows. Accounts doesn’t, because the update went to a WhatsApp group that accounts isn’t in. The 20% installation invoice waits until someone remembers, and on a ₹19 lakh milestone every week of delay is a week of your money sitting with the client.

2. Partial receipts are tracked in a separate sheet

The client pays ₹30 lakh against a ₹47.5 lakh dispatch invoice and says the balance will follow after internal approval. Someone notes it in a receivables sheet. Three months later nobody is sure whether the ₹17.5 lakh was paid, adjusted against a credit note, or never chased.

3. Retention money is forgotten

A 5% or 10% retention due 12 months after commissioning is easy to lose. By then the project team has moved on and the release condition is buried in a contract PDF on somebody’s laptop.

4. Nobody can see receivables per project

Tally will tell you what a client owes in total. It won’t tell you that the Pune cold storage job has its dispatch payment overdue while the Ahmedabad job is still waiting on a commissioning date. Without a per-project view, collections follow-up turns into calling whoever owes the most.

Milestone billing for solar projects: tie each milestone to a stage

Every billing milestone should be linked to a project stage that the site team already updates. When the project moves to “Material Dispatched”, the dispatch invoice is due. When the installation checklist closes, the installation invoice is due. Accounts sees this on the project without waiting for a call from site.

A working setup has these pieces:

For the execution side (surveys, BOM and AMC), see our guide to solar project management software in India.

GST invoice for solar EPC: get the treatment from your CA

How a solar power generating system is treated under GST, including how the contract value is split between goods and services, depends on how your contract is written and on the rules in force when you bill. Those rules get revised, so we won’t quote rates here. Confirm the current rates and the split with your CA before you set up invoice templates, and check again whenever the GST Council announces changes.

Whatever the rate, your billing system should handle:

Keep Tally for the books and run milestones alongside it

Few EPCs want to move their statutory accounting, and there’s no need to. But Tally doesn’t know about roof surveys, BOM shortfalls, installation checklists or which stage a project is in. So the milestone schedule ends up in Excel, stage updates end up in WhatsApp, and accounts sits in the middle trying to match them.

A cleaner split: Tally keeps the statutory books, and milestone invoicing and collection tracking run in a system that knows the project.

Checklist before each milestone invoice goes out

Accounts should be able to tick all of these without phoning anyone:

If a box needs a call to site, the process still depends on someone’s memory.

How Entifly works as solar EPC billing software

Entifly’s Solar & Renewables system is built around this flow. A signed proposal becomes a project, and the client PO, mobilisation advance and milestone schedule are linked to that project record. You define your own payment milestones (20/50/20/10 or any other split), and each one shows its status on the project, such as Received, Upcoming or Pending Milestone.

When a milestone is reached, you raise the tax invoice against it from the project. The project shows the total contract value, the amount received and the balance due. Partial receipts are recorded as payments against the invoice, and the invoice’s Total Paid and Balance Due follow those payments. Each customer also has a ledger of what was invoiced and what was paid, which replaces the separate receivables sheet.

A few other parts help with collections. The Sales & Billing module prints GST invoices with your bank details and a UPI QR code, working out CGST/SGST or IGST from the client’s state. Notifications flag overdue project milestones and payment follow-ups. On the Growth and Business plans you can share invoices and milestone payment reminders straight to the client’s WhatsApp. The owner dashboard shows active sites by stage and payments due.

You can also add custom fields and stages for DISCOM approval, net metering or subsidy release. These are stages your team updates; Entifly does not connect to DISCOM or subsidy portals.

You can keep using Tally for statutory accounting while Entifly runs operations, with every invoice and payment on the project record.

With Kickstart onboarding, our team sets up your project stages, imports your item catalogue, customers and active sites from Excel, and configures milestone payment alerts with you. Plans are on our pricing page: Starter is ₹999/month for up to 15 users, and Growth (₹4,999/month) and Business (₹9,999/month) include unlimited users. Prices are billed yearly, plus GST, and every paid plan has a 14-day free trial.

Frequently asked questions

What is a typical payment schedule for a C&I solar project in India?

One common split is 20% advance, 50% on material dispatch, 20% on installation and 10% on handover. It varies by client, and some contracts add retention or tie the last payment to net metering.

What GST rate applies to a solar EPC contract?

It depends on how the contract is structured and on the current GST rules for solar power generating systems, including the goods and services split. Confirm the current treatment with your CA before you set up your invoices.

How do I track partial payments against a milestone invoice?

Record each receipt as a payment against the invoice. In Entifly, the invoice’s Total Paid and Balance Due update from its payments, so you can see what is still due on each milestone.

Can Entifly track retention money?

Yes. Add retention as its own payment milestone on the project, with its own amount, and add a custom release-date field if you want one. It then stays on the schedule instead of in a contract PDF.

See milestones and receivables per project

If your milestone schedule lives in Excel and your stage updates live in WhatsApp, accounts will keep finding out late. Put both on the project record.

Start a 14-day free trial with the Solar System pre-installed, or book a solar demo and we’ll walk you through milestone billing on a sample C&I project.