Solar Inventory Management Software: Track Every Panel From Godown to Site
At 7:30 in the morning the site lead calls the store keeper: “Load 40 panels and two drums of DC cable for the Chakan job, the truck is outside.” The panels go. Nothing gets written down, because the truck is outside.
This post is about solar inventory management software for Indian rooftop and C&I EPCs, and the godown habits it has to replace. If your stock register is a notebook, your BOM is an Excel file on the project manager’s laptop and material moves on phone calls, you find out what went missing only when someone counts. That is often weeks after the job has closed and been billed.
Where solar material leaks
Panels and inverters are expensive and easy to count. They still go missing, because the losses happen at the handovers between godown, truck and site.
- Material leaves on a verbal request. The store keeper means to update the register in the evening and doesn’t get to it.
- Returns never get logged. A project closes with half a drum of DC cable, a box of MC4 connectors and six spare clamps. They come back on the next tempo and go straight onto the shelf, so on paper that project consumed them.
- Site-to-site transfers go unrecorded. “Take 10 panels from the Shamirpet site to Kompally, we’ll adjust later.” Nobody adjusts later.
- Reconciliation happens late. Stock gets counted at month end, or when a site reports a shortage, and by then nobody can say which job used the extra 300 m of cable.
- Trading sales eat project stock. A dealer calls for 50 panels, the godown has 60 on the floor, and the sale goes through. Those 60 were meant for next week’s job.
Most of these losses are paperwork gaps. The only record of the movement was a WhatsApp message, and it scrolled out of view the same afternoon.
What solar inventory management software should track
The fix is four numbers per item per project, kept in one place that the owner, the project manager and the store keeper all read. Any solar EPC software you evaluate should show them on the project record itself.
A BOM on every project: required, reserved, issued, short
Every project gets its own bill of materials, and each line carries four quantities:
- Required is what the design needs.
- Reserved is what you’ve set aside in the godown for this job.
- Issued is what has physically left for site.
- Short is what you still have to buy.
With those four side by side, the project manager can open the project instead of calling the store keeper. If DC cable is 200 m short, they can see it before the truck is loaded.
Site-wise material issue and returns
Every issue should name the project it’s for. A panel issued “to site” without a project name can’t be traced later.
Returns need the same discipline. When leftover cable comes back, someone logs it against the project it came from. The project’s real consumption stays correct and the godown count goes back up.
Free stock vs reserved stock
Your physical count is not what you can sell. If 1,240 panels are on the floor and 893 are reserved for four active sites, you have 347 to work with. Book 200 of those for a trading order and 147 are free. The sales team needs that last number before they promise anything to a dealer.
Purchase orders for the short items
The short column is your purchase list. Raise a purchase order against it, and when the goods arrive, receive them into stock so the count updates. Purchase and stores then work from the same list.
Low-stock list
Set a reorder level for fast-moving items like DC cable, MC4 connectors, earthing material and structure clamps. Check one list of everything at or below that level each day, so you hear about a shortage before a site calls.
Sample BOM for a 100 kWp C&I rooftop
Here is what a project BOM can look like midway through execution. The quantities are illustrative only. Your designer’s numbers will depend on module wattage, string design, roof layout and cable routing.
| BOM item | Unit | Required | Reserved | Issued | Short |
|---|---|---|---|---|---|
| Mono PERC module 545 Wp | Nos | 184 | 184 | 184 | 0 |
| String inverter 50 kW | Nos | 2 | 2 | 2 | 0 |
| Module mounting structure (rails, clamps, fasteners) | Set | 1 | 1 | 1 | 0 |
| DC solar cable 4 sq mm (red + black) | m | 1,200 | 1,000 | 1,000 | 200 |
| MC4 connector pairs | Nos | 24 | 24 | 20 | 0 |
| AC cable from inverter to ACDB | m | 60 | 60 | 0 | 0 |
| ACDB with MCB and SPD | Nos | 1 | 1 | 0 | 0 |
| Earthing kit (chemical electrode + compound) | Nos | 3 | 3 | 0 | 0 |
| Lightning arrester | Nos | 1 | 1 | 0 | 0 |
| Cable tray and conduit | m | 80 | 40 | 40 | 40 |
What the table tells you:
- Panels, inverters and structure are fully issued, so mechanical work can go ahead.
- 200 m of DC cable and 40 m of cable tray are short. Purchase needs to order them before the DC cabling crew reaches that part of the roof.
- The AC side material is reserved but still in the godown. It goes out when the electrical team is scheduled.
- Four MC4 pairs are still in the godown. If the site asks for them, you know they’re available and already set aside for this job.
When the job closes, compare issued against what was actually installed. Any gap is either a return you still have to log or material you need to explain.
One godown, two businesses
Many EPCs also trade panels and inverters to smaller installers and dealers, often from IndiaMART enquiries. The trading money helps cash flow, but it makes the stock count harder to trust.
Keep both businesses on one stock pool and make the split visible:
| Panel 545 Wp | Qty |
|---|---|
| Physical stock in godown | 1,240 |
| Reserved for 4 active projects | 893 |
| Booked for trading orders | 200 |
| Free to sell | 147 |
Project material goes out through each project’s BOM. Trading sales go out on their own GST invoices to the dealer’s ledger. Both draw from the same count, so before the owner agrees to a dealer order, they can see how much of the stock is already promised to sites.
A store keeper’s daily checklist
Software only helps if the routine around it holds. A short daily routine for whoever runs the godown:
- Nothing leaves without an issue entry against a named project or a trading invoice.
- Every return from site is logged against the project it came from, the same day.
- Site-to-site transfers are logged as a return from one project and an issue to the other.
- The low-stock list is checked before noon, so purchase has time to order.
- Short items on active BOMs go to purchase with the date the site needs them.
- Damaged or broken modules are recorded as an adjustment, with the reason written down.
- One high-value item (panels or inverters) gets a spot count each week, compared with the system.
How Entifly handles solar inventory and BOM
Entifly’s Solar System connects leads, site surveys, quotations, projects, warehouse stock, milestone billing and AMC in one workspace. On the inventory side:
- Every project has its own bill of materials. Material is reserved from your warehouse stock and marked as issued when it’s dispatched to site, so you can see what was required, what went out and what is short.
- Turnkey projects and wholesale orders to dealers draw from the same stock. Trading sales get their own tax invoices and customer ledgers, and you see the physical count, the stock allocated to sites and the free quantity available to sell.
- Set a reorder point on each item and the Low Stock Items widget on your dashboard lists everything at or below it. A Low Stock Alert automation can also notify a person you choose, once you switch it on.
- The Inventory ledger records purchases, sales and adjustments. Entries are read-only once saved, so you correct a mistake with a new adjustment entry and the original stays on record.
- Add the Purchasing module to raise purchase orders for short items. Marking an order received adds each line’s quantity to stock. The Solar System uses most of the Starter plan’s custom entities, so you’ll usually want Growth or Business for this.
- Store keepers can be limited to inventory and material issues, and site engineers to their own sites.
- You can import your item catalogue, dealer contacts and open projects from Excel or CSV. If you run your own project stages or need extra fields, we’ll help you set up that workflow during onboarding.
- Entifly runs daily operations and GST invoicing. Your accountant can keep using Tally for statutory accounts.
To track ALMM or DCR status, module serial numbers or batch numbers, add a custom field to your items or projects. DISCOM, net metering and subsidy steps work the same way: they are stages and custom fields you set up, and Entifly does not connect to those portals.
One limit to know before you sign up: each item has a single stock count. If you run two godowns, Entifly won’t show them as separate stock locations yet.
For the project side (site surveys, installation checklists, milestone billing and AMC), read our guide to solar project management software in India.
Pricing is flat. Starter is ₹999/month for up to 15 users. Growth is ₹4,999/month and Business is ₹9,999/month, both with unlimited users, so every store keeper, site engineer and technician gets their own login. Prices are billed yearly, plus GST, and every paid plan has a 14-day free trial. The pricing page lists what each plan includes.
FAQ
Can I see how much material went to each site?
Yes. Each project’s BOM shows what was required, reserved, issued and short for that site.
We sell panels to dealers too. Will trading sales eat into project stock?
Both draw from one stock pool, and Entifly shows stock reserved for projects separately from free stock. Your sales team can check what is actually free before quoting a dealer.
Does Entifly reorder stock automatically?
No. Items at or below their reorder point appear on your dashboard, and you can switch on an alert that notifies someone. A person still decides what to order and raises the purchase order.
Can I track panel serial numbers or ALMM status?
Add a custom field to track serial numbers, batch numbers or ALMM and DCR status. These aren’t built-in fields, but adding one takes a few minutes and needs no code.
Try it on your next project
Load one active project and its BOM, issue material against it for a week, and check whether the end-of-week count matches the godown. Start your 14-day free trial with the Solar System, or book a demo from the solar EPC software page and we’ll walk through it with your own items.